Project status report

Mark Anglin, PMP

Given the following project network, baseline, and status information, develop the status report for period 6 and complete the

performance indices table. Based on your analysis, what is your assessment of the current status of the project? Show all your

calculations.

When complete and ready to hand in, name your file with your name and section as follows : ASSIGN5_Name_Nxx

Status Report: Ending Period 6
Task % ($000)
Complete EV AC PV CV SV
A 100% ? 35 40 ? ?
B 85% ? 24 32 ? ?
C 60% ? 24 24 ? ?
D 0% ? 0 6 ? ?
E 45% ? 10 8 ? ?
Cumulative Totals ? 93 110 ? ?

Performance Indexes Summary
Period EV AC PV SPI CPI

6
108.6
93
110
98.727
116.774